Greetings all, marina opening activities are going well and see below points with much more to do:
Water is on to our washrooms
Office is cleaned up
amp has been cleared of sand and new walkway to floating docks installed
Longer ramps are in the grass area and will be installed on B & C dock shortly after lift in. I am not sure when they were last used but the decking is rotten and I will fix them soon.
Diesel sales are going well and Cottrils will be buying the last 300 litres early next week.
We have 4 people prepared to help lower A dock the weekend before lift in and looking for 4 more helpers
Piling for the new fuel dock is now on the ground and will be thumped in by dredging contractor
Pre job meeting for dredging is on 11 April.
Rob